Image: Voice of America
Updated
Turkmenistan expects to complete the 153-kilometre Serhetabat-to-Herat segment of the TAPI gas pipeline by the end of 2026, with gas deliveries to Afghanistan expected in early 2027. The $10 billion Turkmenistan-Afghanistan-Pakistan-India project faces challenges from Taliban rule and security concerns, Voice of America reported. VOA reported, citing Reuters, that Turkmenistan has largely financed recent construction itself because international lenders and private investors remain reluctant. Few governments formally recognise the Taliban, and the Asian Development Bank paused regular aid to Afghanistan after the 2021 takeover, saying future assistance depends on circumstances and approvals. Afghan analyst Ahmad Sear Quraishi said cheaper gas could cut factory costs, with Afghanistan initially buying 500 million cubic metres a year, but warned that Kabul-Islamabad tensions and India-Pakistan disputes could complicate onward supply to Pakistan and India.